3 min learnMumbaiFeb 12, 2026 12:47 AM IST
The Bombay Excessive Court docket on Wednesday levied 5 per cent every year interest on compensation to be paid by the Brihanmumbai Municipal Company (BMC) to the Nationwide Sports activities Membership of India (NSCI) in Worli for utilizing its premises for Jumbo Covid Centre through the pandemic.
It requested the civic physique to deposit by March 16 the interest quantity for almost three years since April 2023 on Rs 12.66 crore compensation calculated by it and permitted NSCI to withdraw the identical pending listening to of its plea.
The NSCI had approached the excessive court docket final yr, claiming that just about Rs 40.11 crore was resulting from it as compensation.
A bench of Justices Ravindra V Ghuge and Abhay J Mantri of HC on February 5 had questioned the “inaccurate” estimate given by the BMC for cost of compensation for utilizing NSCI facility as a Jumbo Covid Centre for 30 months through the pandemic.
The court docket had cited “large distinction” between the calculations of the petitioner and the BMC and had sought private clarification from BMC commissioner Bhushan Gagrani.
The civic physique had denied the petitioner’s claims, stating that it had not used the open space across the constructed Jumbo Quarantine Centre.
On Wednesday, senior advocate Atul Damle submitted Gagrani’s affidavit dated February 6 and “painstakingly tried to influence” the court docket to simply accept the contents in affidavit being “believable and justifiable conclusion by the BMC” of arriving at a determine of Rs 12,66,56,278.9 in direction of token cost of compensation to the petitioner towards the declare of almost Rs 40.11 crore
Story continues under this advert
“Prima facie, a lot must be stated concerning the calculations and justifications made by the Commissioner,” the bench famous.
“However, since a selected quantity has been admitted and stated determination was taken as on April, 2023 and since it’s but to paid to the petitioner, we deem it acceptable to levy interest at 5% every year until March 16, 2026, to be deposited on this court docket.”
The HC stated the NSCI can withdraw the interest quantity by giving an endeavor that it’ll redeposit the portion of quantity inside 30 days if, after remaining adjudication of the plea, it’s discovered to be in extra of what was payable to the petitioner.
“This sediment by Company and withdrawal by petitioner might be with out prejudice to their rights and competition. Nonetheless, we make clear if there are any outstandings in direction of petitioner purportedly in direction of property taxes, BMC could provoke acceptable process below the statute,” the bench famous and posted additional listening to to March 18.